KINGSTON STATE COLLEGE BLOCK G REFURBISHMENT
Project Details
Duration:
8 weeks construction
Size:
830m2 approx.
Completed:
2020
Building Class:
Class 9
Location:
50 Juers Street, KINGSTON
Work:
Design & Construct by Future Fitouts
Project Overview
A design and construct refurbishment of Block G at Kingston State College. Works included the replacement of the existing roof, new ceiling, building works, brick and blockworks, flooring, service trades (mechanical, electrical and hydraulic) and minor external works with some landscaping.
Key Learnings
Engaged to manage and coordinate all trades to deliver an 830m2 refurbishment of Block G, the Future Fitouts team worked within a live school environment ensuring the safety of students, teachers and stakeholders. Key challenges included ensuring all building aspects were bought up to AS Standards as well as working closely with an external certifier to meet current code requirements. Asbestos was also found in the building and had to be removed from the building in a safe and secure manner.